Grenoble Drive to Marseille Drive
COMPLETED
This project consists of the reconstruction of the existing roadway with new pavement, curb & gutter, sidewalk, ADA-compliant curb ramps, signage, pavement markings, and minor drainage improvements, with upgrades to illumination, water, and wastewater utilities.
August 22, 2023:
The contractor has completed the new roadway and all utilities from Grenoble Drive to Blankenberge Drive. They are working on the remaining sidewalk and placing limestone base on the roadway from Blankenberge Drive to Marseille Drive. The project is set to be completed by the end of September.
July 19, 2023:
The Strasbourg Drive project is currently 75% complete. The contractor is currently working on curb and driveway installations from Grandvillers Dr. to Marseille Dr. In the coming weeks, they will begin working on sidewalks and paving the roadway.
June 9, 2023:
The contractor is currently installing the road base, curb and gutter. They have completed all utility work and anticipate the full project to be completed this Fall.
March 6, 2023:
The contractor has completed the wastewater line installation and is currently working on both the water and storm water line installations this week. Once complete, they will work on the roadway excavation in preparation for lime stabilization.
View the official project blueprint with proposed improvements.
Location (Satellite) »Public Information Officer, Chloe Swan Rybalka | 361-826-3528 | chloes2@cctexas.com