FM 624 to Wood River Drive
Rehabilitation of existing 2-lane roadway with new pavement, sidewalk repairs, curb and gutter, installation of ADA-compliant curb ramps, signage, pavement markings, and upgrade/add street illumination.
August 24, 2023:
The contractor is currently pouring driveways and hauling limestone base on the east side of Trinity River. The project is scheduled to be completed by the end of the year.
July 25, 2023:
The contractor for the Trinity River project is currently installing the 8-inch waterline on the east side of the roadway. Once complete they will move to the west side.
View the official project blueprint with proposed improvements.
Proposed Work »Public Information Officer, Chloe Swan Rybalka | 361-826-3528 | chloes2@cctexas.com