Engineering Logo

Wildcat Drive

FM 624 to Teague Lane

This project consists of the rehabilitation of an existing 2-lane roadway with shoulders with new pavement, minor sidewalk repairs, and installation of two ADA-compliant curb ramps, signage, and pavement markings. Various street utility improvements include stormwater, wastewater, water, and gas.

1Phase 3 Map
nProject Updates

October 27, 2023:
The contractor is currently installing fire hydrants, storm inlets, and storm boxes on the Wildcat Drive project.

September 22, 2023:
The contractor is currently installing fire hydrants, storm inlets, and storm boxes on the Wildcat Drive project.

August 24, 2023:
The contractor has completed installing curb, gutter, sidewalks and underground utilities in Phase 3 of the project. They’re currently working on the second part of Phase 2.

July 13, 2023:
The contractor has completed Phase 1 of the project. They are currently moving on to Phase 3 and are working to install inlet boxes and waterlines.

June 9, 2023:
This week the contractor is working on pouring concrete for curbs, gutters, and driveways. Next week, the will begin prepping the roadway for base material.

March 3, 2023:
The contractor has completed the saw cutting of driveways and sidewalks and is currently installing storm inlet boxes. Traffic is one-way from FM 624 to Teague Lane.

tProject Facts

Find basic info about the project and contractor.

View Facts »
1Project Maps

View the official project blueprint with proposed improvements.

Project Exhibit »
!Project Contacts

Have questions? Find answers from City representatives.

View Contacts »

Questions?

Sr. Public Information Officer, Melanie Lowry | 361-826-3837 | MelanieL@CCTexas.com

© 2020 City of Corpus Christi