Brawner Parkway

Carroll Lane to Kostoryz Road

The construction will include new asphalt pavement, curb and gutter, driveways, storm water drainage improvements, potable water improvements (domestic water distribution and fire protection), wastewater improvements, gas line improvements, traffic signal improvements, and construction of ADA-compliant pedestrian improvements, pavement markings, signage, traffic control, and additional Right of Way (ROW) acquisition.

nProject Updates

April 19, 2022: The Brawner Parkway project contractor has installed new storm water laterals and inlets on the South side of the roadway. They have also installed a new waterline on the South side moving North through the existing ditch. The contractor is currently working on the installation of curb and gutter and expect to continue this work over the coming weeks. Motorist can anticipate a traffic switch on the North side of Brawner Parkway with one-way traffic heading westbound so that the contractor can begin installing a new waterline along the ditch area.

November 19, 2021: The Brawner Parkway project is currently under construction. The contractor is working to install a new sewer line and manholes on the South side of the roadway of Brawner Parkway. Currently 1800’ of waterline has been installed including fire hydrants. Testing will be done on the news waterlines in the coming weeks.

Brawner Parkway Construction Begins Next Week »
OCTOBER 8, 2021

tProject Facts

Find basic info about the project and contractor.

View Facts »
1Project Maps

View the official project blueprint with proposed improvements.

TCP Phase 1A »
Location Map »
Cross Section »
Plan View »
!Project Contacts

Have questions? Find answers from City representatives.

View Contacts »

Questions?

Sr. Public Information Officer, Melanie Lowry | 361-826-3837 | MelanieL@CCTexas.com

© 2021 City of Corpus Christi