Bear Lane to Old Brownsville Road

This project is to construct Segment 1 and Segment 2 simultaneously. This project will reconstruct the existing Junior Beck Drive (Segment 1) with a two-lane roadway, curb & gutter, sidewalks, ADA ramps, pavement markings, signage, utility improvements include upgrades to water, wastewater, storm water, gas and build the new roadway (Segment 2) from the dead end to Old Brownsville Road with a two-lane roadway, safety illumination, cross culverts, and drainage swales on both sides. This project will improve road access and promote further development and growth in the area.

nProject Details

Segment 1: Junior Beck Drive from Bear Lane to Dead End is classified as a minor residential collector with 0.622 miles in length. This section of street was originally constructed in 1980 and was reconstructed again in 1992. The road consists of a two-lane asphalt roadway with curbs, gutters, and sidewalks that are in poor condition with aging underground utility systems. Junior Beck Drive currently supports industrial and commercial activity with heavy commercial vehicle traffic with only one access point from Bear Lane.

Segment 2: Junior Beck Drive from Dead End to Old Brownsville, is a planned (never built) Minor Residential Collector with 0.321 miles in length.

nProject Updates

April 25, 2022: The Junior Beck Drive project recently began. The contractor has started Phase 1 of the project and is working on clearing the right of way. Crews are also televising the existing utilities which will continue next week.

tProject Facts

Find basic info about the project and contractor.

View Facts »
1Project Maps

View the official project blueprint with proposed improvements.

Proposed Improvement »
Location Map »
!Project Contacts

Have questions? Find answers from City representatives.

View Contacts »

Questions?

Sr. Public Information Officer, Melanie Lowry | 361-826-3837 | MelanieL@CCTexas.com

© 2021 City of Corpus Christi